Timeline

2003 Current Comprehensive Plan adopted
2006 Downtown Character Committee formed and public process initiated
2007 Downtown Character Plan and first Neighborhood Plan adopted
July 2008 Golden selected the Foundation as Heart & Soul Community Planning town
Dec. 2008-Feb. 2009  Work plan and project website developed; advisory group formed
March 2009 Project launch event held
March-Sept. 2009  Heart & Soul identification and storytelling
Mar.-Oct. 2009 Scenario development and analysis
Jan.-Oct. 2010 Implementation recommendations developed from public meetings
Nov. 2010 Monitoring and stewardship of Neighborhood and Downtown Vision Plans
Ongoing Project monitoring and evaluation